Project By: Hi-Tech Ultra Homes Pvt. Ltd.
 
Occupancy Certificate Received - March 2017

Occupancy Certificate - A

Occupancy Certificate - B
Updates
Applied for Occupancy Certificate Applied for Occupancy Certificate - Part 1 Applied for Occupancy Certificate Applied for Occupancy Certificate - Part 2 Fire NOC Page No. 1 Fire NOC Page No. 1 Fire NOC Page No. 2 Fire NOC Page No. 2
Lift No.1-Maharashtra Govt. License.Lift No.1 - Maharashtra Govt. License. Lift No.2-Maharashtra Govt. License.Lift No. 2 - Maharashtra Govt. License. Drainage connection certificate CIDCODrainage connection certificate CIDCO Water connection NOC CIDCO Water connection NOC CIDCO
HEALTH NOC CIDCOHEALTH NOC CIDCO Structural Stability CertificateStructural Stability Certificate 100% Completion Certificate100% Completion Certificate CC Page No. 1CC Page No. 1
CC Page No. 2CC Page No. 2 CC Page No. 2CC Page No. 3    
Completion of Project November 2016
Work in Progress September 2016
Work In Progress February 2016
Competion of R.C.C. Work and Brick Work November 2015
16th Slab Completion August 2015
15th Slab Completion July 2015
14th Slab Completion April 2015
12th Slab Completion February 2015
10th Slab Completion December 2014
8th Slab Completion November 2014
7th Slab Completion September 2014
5th Slab Completion August 2014
1st Slab Completion May 2014
Underground Water Tank Completion March 2014
Plinth Level Completion February 2014
Foundation Work January 2014
Commencement Of Work December 2013